|











| |
|
buildings > Schools |
| |
|
|
| |
Washoe County School District, Spanish Springs & North Valley High Schools
Reno, Nevada, USA
Washoe County School District
undertook construction of two new high
schools. The schools were identical in
design, albeit prototypes relative to past
construction. County building officials
surprised all parties upon rejecting the
design team’s design, citing violations to
fireproofing codes in that the architect had
been coordinating design efforts with the
officials for several months prior to the
rejection notice. After failed attempts to
challenge the ruling, the school district
still agreed to proceed with the awarded
contract. A major design change was made to
each school to allow for a Type II, 2-hour
fire rating that included reducing room
sizes and use of monokote-type fireproofing.
Nielsen-Wurster performed a delay and
causation analysis to determine equitable
adjustment to the contractor for time
impacts caused by the design change. The
contractor intended to file an early
completion claim in addition and sought
compensation for acceleration in meeting its
proposed early completion dates.
Nielsen-Wurster’s analysis concluded that
the contractor had failed to meet criteria
for an early completion claim. Further,
Nielsen-Wurster’s analysis concluded that
the school district had already
over-compensated the contractor for alleged
acceleration. Nielsen-Wurster assisted in a
mediation where the architect and school
district reached a settlement. A favorable
settlement was also reached with the
contractor a few months later.
|
|
| |
|
|
| |
Montbello Parkfield Middle School
Denver, Colorado, USA
Nielsen-Wurster was engaged by The
Denver Public School District (DPSD)
to provide an independent evaluation
of the project status, work completed
as of the review and the issues
associated with the effort required to
complete all contract scope.
Nielsen-Wurster presented to the DPSD
a summary opinion with respect to
project status, responsibilities for
the delays, and an assessment of the
contractor’s project management.
Nielsen-Wurster also evaluated the
status of the project based on the
billings and physical percent complete
and advised DPSD of areas where the
Contractor may submit claims for
additional costs, and what the
approximate damage might be.
|
|
| |
|
|
| |
Fairmont State College Classroom Buildings
Fairmont, West Virginia, USA
At the time of
Nielsen-Wurster's analysis, this Fairmont
State College renovation project of
classroom space and a dining facility was
delayed two to three months and had incurred
a substantial number of change orders. The
Contractor requested a time extension for
the full delay period and extended general
overhead costs. The State of West Virginia
alleged that the Contractor mismanaged the
construction work. Major Project issues
included unforeseen site utilities, utility
relocations, design changes to window
detailing, asbestos removal and construction
staging between the three different
buildings. Nielsen-Wurster performed a
preliminary delay analysis and entitlement
review on behalf of the Owner for use in
negotiation of a time extension and
additional compensation to be granted to the
Contractor on the Project. Nielsen-Wurster
analyzed the Contractor's claim, including
the schedule, Project changes and
documentation, and made an initial
determination of responsibility for the
various delays. The claim reached a
settlement, based on Nielsen-Wurster's
analysis.
|
|
| |
|
|
| |
Southwest State University Recreation Center/Athletic Facility
Marshall, Minnesota, USA
Nielsen-Wurster analyzed a Contractor
request for an extension of time resulting
from a fire which damaged a portion of the
construction work and contributed to delays
in the Recreation Center/Athletic Facility
Project at Southwest State University in
Marshall, Minnesota. Nielsen-Wurster
reviewed the initial Project schedule and
updates before the fire to ascertain the
true progress on the Project. Contractor
staging and manpower during the
reconstruction period were analyzed to
determine whether inefficiencies existed in
the approach to this work. In addition, a
Window Analysis was performed during the
immediate time period after the fire
utilizing the Contractor's monthly schedules
to determine the overall critical delay to
the Project completion date. Results of the
Nielsen-Wurster analysis were used to
negotiate a time settlement for this
incident with the Contractor during the
construction process.
|
|
| |
|
|
|
BACK TO TOP |
|