|











| |
|
Transportation >
Airports |
| |
|
|
| |
 |
|
| |
|
|
| |
Osborne Cogeneration Gas-Fired Power
Plant
Adelaide, South Australia
This gas-fired cogeneration plant located in South
Australia experienced substantial completion delays
prior to steam blow and commencement of commissioning,
which the Owner maintained were indisputably caused by
the Contractor. Further, the effective date of the
Certificate of Acceptance was also in dispute, and
between that date and the extended Guaranteed Acceptance
Date, the Owner charged the Contractor with the maximum
liquidated damages. The Contractor served a dispute
notice on the Owner, claiming liquidated damages
deducted and enhanced incremental costs for Owner-caused
delays. Nielsen Wurster was engaged to prepare a
schedule delay analysis and to address Contractor’s
allegations of delay. Nielsen-Wurster reviewed the
project documentation, schedules and start-up records,
and prepared an expert analysis to be employed in the
negotiations. After Nielsen Wurster met directly with
the Contractor’s scheduling consultant and presented the
findings of their analyses, the Contractor and Owner
were able to reach an amicable settlement in which a
portion of the liquidated damages were forgiven without
payment of enhanced incremental costs.
|
|
| |
|
|
| |
Nikiski Cogeneration Facility
Nikiski, Alaska,
USA
Nielsen-Wurster was engaged by the project Developer to evaluate
the turnkey Contractor’s claim on the Nikiski Cogeneration
facility, which provides steam to a local fertilizer plant and
generates 40 MW of power which is sold to the local utility.
This cogeneration plant was built using a relocated gas turbine
generator which was then connected to a new package HRSG that
supplies steam to the fertilizer plant. The Contractor’s claim
included issues relating to the gas turbine generator, delivery
of the HRSG contract and alleged interference and changes
imposed by the Owner during design and construction.
Nielsen-Wurster prepared a counterclaim report and detailed
evaluation of the opposing expert’s report, specifically
analyzing such issues as the Contractor’s project management,
Owner’s administration of the contract, schedule delays,
construction productivity, reasonableness of the Contractor’s
bid and damages incurred. Following significant mediation
presentations by Nielsen-Wurster and the results of its
analyses, the Contractor accepted a settlement that was less
than 20 percent of its claim.
|
|
| |
|
|
| |
Conoco Cogeneration Plant
Orange, Texas
Nielsen-Wurster was engaged by the Owner of a cogeneration
facility to provide expert analyses in a dispute with the
Engineer-Procure-Construct (EPC) Contractor, after the Owner had
exhausted all attempts to reach an amicable settlement on this
combination lump sum turnkey (LSTK) / time and materials (T&M)
project. The Owner claimed damages as a result of Contractor
project delays, willful slowdown, excessive T&M costs and LSTK
overpayments. Nielsen-Wurster reviewed the claim documents and
project records, prepared a schedule delay and causation
analysis, and evaluated all parties’ project management.
Nielsen-Wurster presented its results in a mediation that led to
resolution of all issues between the parties.
|
|
| |
|
|
| |
Elsta
Cogeneration Power Plant
Terneuzen, The Netherlands
Nielsen-Wurster was engaged by AES International
Corporation, the Owner/Operator of a 400 MW cogeneration
power plant located adjacent to a chemical company’s Benelux
facilities. The plant provides process steam and electrical
power to the chemical plant and excess power to others. At
what was scheduled to have been mechanical completion, AES
bought the project from a subsidiary of the chemical company
that was executing the project through another chemical
company subsidiary under a lump sum turnkey contract. There
were allegations of misrepresentation of the adequacy and
level of completion of design at the time of the sale. In an
International Chamber of Commerce (ICC) Arbitration,
Nielsen-Wurster presented expert analyses on the chemical
company’s various subsidiaries’ project management, the
impacts sustained from delay/acceleration/disruption, and
AES’ management, scope and costs of corrective measures
undertaken following completion.
|
|
| |
|
|
| |
Lakewood Cogeneration Plant
Lakewood, New
Jersey
The Engineer-Procure-Construct (EPC) Contractor (CRS
Sirrine, Inc.) engaged Nielsen-Wurster to perform Risk
Management and Dispute Resolution Services on this 236 MW
Combined Cycle Cogeneration Plant in Lakewood, New Jersey.
The plant had two gas turbines (Type ABB CT 11N1) with Dry
Low Nox combustion chambers, each with a dedicated
generator. Each gas turbine was coupled to an individual
unfired Heat Recovery Steam Generator (HRSG) that exhausted
through a separate stack and a single casing steam turbine.
The scope of work also included the buildings, switchyard,
water treatment facilities, fuel storage facilities and the
associated site improvements. The Project experienced
numerous delays, acceleration claims from the Prime
Contractors and start up problems, including a catastrophic
equipment failure and inability to meet the prescribed and
state mandated emission levels. Additionally, the economic
basis of the plant was impacted by the noncompletion of the
steam user (a greenhouse facility) that was terminated about
90 percent into completion of the power plant. The Developer
blamed many problems on the EPC Contractor and the primary
Subcontractors and equipment Vendor. Nielsen-Wurster
initially assisted on-site with resolving the Project
completion issues. Following the catastrophic accident (with
turbine related equipment), Nielsen-Wurster analyzed the
causes for delay and subsequent acceleration and cost of
Subcontractor-claimed productivity impacts. The results of
Nielsen Wurster’s analyses were employed to resolve all
issues between the Owner/Developer and the EPC Contractor,
and between the EPC Contractor and the primary
Subcontractors and equipment Vendors. The resolution was
provided in a timely fashion so the CRS power subsidiary
could be sold to a new Owner.
|
|
|
BACK TO TOP |
|