|







| |
|
Transportation >
Bridges |
| |
|
|
| |
 |
|
| |
|
|
| |
Tsing Ma Bridge
Hong
Kong
The Tsing Ma Bridge is a
combined highway and railway suspension bridge
consisting of two portal-type concrete towers,
each 200 meters tall, that support the
bridge's 2,172-meter length (1,377-meter clear
span). The bridge forms an integral part of
the transport network linking the Hong Kong
Airport at Chek Lap Kok with Kowloon and Hong
Kong Island. The Bridge was commissioned by
The Government of Hong Kong, Highways
Department (Government). The Government
accepted a tender for the Project by an
Anglo-Japanese Construction Joint Venture (JV)
for a Contract period of 60 months. Nielsen-Wurster
was engaged by the Government's Counsel to
perform a schedule delay analysis to validate
schedule impacts of the JV's claim that it
incurred significant cost overruns in
accelerating construction due to two principal
issues: The Government's imposed concrete
specification was too strict, thereby
rendering an approved mixture impossible to
attain; and because of Government-attributable
delays related to concrete and other late
approval issues, the JV was forced to alter
its means and methods by using two sets of
slipforms and constructing the towers in
parallel rather than sequentially with a
single slipform set. Nielsen-Wurster performed
a Window Analysis and identified the
activities that delayed the works and
concurrent delay, including causation for each
delay. These and other relevant findings were
presented in a written Expert Report and also
via expert testimony before an international
Arbitration. While specifics of the arbiters'
ruling are confidential, the Client can be
contacted relative to work efforts performed.
|
|
| |
 |
|
| |
|
|
| |
Houston Ship Channel
Cable-Stayed Bridge
Baytown, Texas
Nielsen-Wurster was jointly engaged by the
Texas Department of Transportation (TXDOT) and
the Contractor to serve as a Project Neutral
to analyze claims and issues on this $96
million fixed price contract for the
construction of a large cable-stayed
suspension bridge over the Houston Ship
Channel. There was a 48.5-month delay in
completion of the bridge and a $70.5 million
claim was filed. As a result of
Contractor-proposed changes to the suspension
cable, bridge deck (from cast-in-place
concrete for each segment to precast panels
for each segment) and cable anchorage, the
design of the structural steel was changed.
The claim alleged design defects by the
engineer, over-inspection by the TXDOT quality
control inspectors, and management
deficiencies by TXDOT. Conversely, TXDOT
alleged General Contractor design changes,
poor workmanship and poor quality control.
Nielsen-Wurster prepared an independent
technical and management evaluation of all the
issues, made recommendations on
responsibility, and proposed a value for
settlement to the Contract Claims Board to
which the parties agreed.
|
|
| |
|
|
|
BACK TO TOP |
|